Progress update on 4561’s side tanks

Progress update on 4561’s side tanks

Before the top sheet was finally put in position the fixing bolts for the air vent, feed pipe bracket and top inspection cover were welded in place. These items cannot be accessed internally once the tank is complete, so the bolts are held captive to allow the parts...
The Manufacture of New Side Tanks for 4561 are Progressing Well

The Manufacture of New Side Tanks for 4561 are Progressing Well

Further Progress is being made on 4561’s at Minehead All of the 10mm holes that were laser cut in the inside platework have now been drilled through and transferred into the angle iron frame. These holes in the frame have now all been drilled out to 10.3mm and...